2024 Quarter Three: Review in Photos
Written By Katie Hynes
KC Streetcar Constructors continued working hard on the KC Streetcar Main Street Extension in the months of July, August and September! Check out this review of Q3 2024 in photos to see some of the progress on the project corridor. A Q3 2024 report is also available here.
View fullsize
Pedestrian upgrades near the Main Street and Westport intersection on July 2, 2024
View fullsize
Installing track drains near the UMKC stop on July 15, 2024
View fullsize
Installation of the southbound Westport shelter on July 17, 2024
View fullsize
Setting the TPSS near UMKC on July 18, 2024
View fullsize
Poured red concrete for the track in a transit exclusive lane on July 19, 2024
View fullsize
Constructing medians on Main Street near 30th Street on July 19, 2024
View fullsize
UMKC Shelter installation as of August 5, 2024
View fullsize
Pedestrian upgrades continue near the Main Street and Linwood Boulevard intersection on August 15, 2024
View fullsize
As of August 27,2024, 100% of the OCS foundations were installed on the project.
View fullsize
Crews pulled wires for OCS poles along the full project site on August 26, 2024.
View fullsize
Set the TPSS on West 44th Street on August 29, 2024
View fullsize
Crews prepared the Main Street Viaduct for connecting the Main Street Extension to the existing streetcar system on August 29, 2024
View fullsize
Landscaping started along the full project in September 2024.
View fullsize
Pouring concrete for the northbound track near Pershing Road on September 19, 2024
View fullsize
Pouring concrete for northbound track near Pershing Road on September 19, 2024
View fullsize
Progress continued on the Midtown Annex near 38th Street & Baltimore Avenue
View fullsize
Poured concrete for part of the streetcar stop at the future Plaza Transit Center on September 20, 2024
View fullsize
New trees planted near Linwood Boulevard in September 2024
View fullsize
A new crosswalk and traffic signal was installed at 37th Street and Main Street in September 2024
View fullsize
Poured part of the overlay for the Main Street Viaduct on September 24, 2024
View fullsize
Markers were installed for many of the streetcar stops!
View fullsize
Progress continues near the Plaza Transit Center on September 24, 2024
View fullsize
Medians were landscaped on Main Street between 27th Street and 31st Street in September 2024
View fullsize
Work began Monday, September 30th to connect the Main Street Extension to the existing downtown streetcar line